DELPHI PACKARD witnesses our expertise and trust us three times for the construction of its production plant in Tangiers, its extension and Kénitra factory extension
Project :
Company: Delphi Packard
Activity: production of electrical wires for cars
Location: Tanger Free Zone – Atlantic Free Zone Kenitra
Construction period : 11 months/factory – 8 months/extension
Dimensions :
* Land 60.000 sqm
* Constructed area – Tanger plant 24.000 sqm
* Constructed area – Tanger extension 7.000 sqm
* Constructed area – Kénitra extension 7.000 sqm
* Workshop frames 20 X 25 m
Main soil constraints- Tangier :
* Marl and sweilling soil
* Seismic zone category 3
* Windy zone catégory 3
Main equipments :
* Electrical equipment
* Air compressed
* Air conditionning
* Sprinklage and RIA
* Fire detection
Main buildings and works :
* Workshop
* Shipping and receiving area
* Technical rooms
* Social premises and offices
* Sanitation
* Roads
* Green spaces